Design a project in the order it is built

ConstructiVision asks you to design a tilt-up job in the same order the crew builds it. Each step depends on the steps before it:

  • The site comes first, because the slab is the casting bed.

  • On a panel, the form must exist before anything is cut from it.

  • Everything on the down face is laid before the reinforcement.

  • Lifting and bracing come last, because they depend on the finished panel’s weight, centre of gravity and openings.

The toolbar runs left to right in this order, so working along it follows the sequence below.

The site, in the order it is built

step

in the field

in ConstructiVision

Units

Imperial or metric for the whole job

CV-UNITS, saved in your AutoCAD profile

Preconstruction

Review site access for equipment, deliveries and the crane. Get the engineered tilt-up package, the approved shop drawings and the bracing manual. Plan the casting and lifting sequence, and choose a crane for the heaviest panel at its reach.

New Project, Project Details

Lay out the building

The structural grid, and the wall lines the panels stand on, with each corner’s condition (butt, bypass or miter)

Site Grid, Walls

Foundations

The footings under the panels, with shim points placed so the footing is not overloaded before grouting

Footing Step, on each panel

Slab-on-grade, except the leave-outs

The slab is the casting bed and the working surface, so it must carry the brace loads and the crane. The closure strip is left unpoured along the panel line so the panels can be set and braced.

Slabs: the slab outline, the closure strip and the brace line

Panel layout on the slab

Where each panel is cast, so the crane can lift it to its place on the wall within its reach

Attach Panels, Construction Layout IN / OUT, Cast Layout Draw

Form and cast the panels

Each panel, in the order in the next section

the panel buttons

Before lift day

The concrete has reached lifting strength. Inserts and braces are checked against the shop drawings, and the crane is rigged and inspected. Ramps let the crane onto the slab, and it never bears on the slab edge.

Pick Points, Brace Points

Lift and set

Each panel is tilted off its casting surface in the planned sequence, set on its shims, plumbed, and braced before the crane lets go

Tilt-Up Panels, Autosite

Steel and roof deck

The roof structure connects to the panels and completes the building’s lateral system

the panels’ weld connections

Pour the leave-outs

The closure strip is poured after the steel and roof deck. Backfill against the panels carefully.

the closure strip set under Slabs

Remove the braces

Only after every structural connection is made, as the engineer of record directs

–

Check and issue

The interference check, QA findings, materials list, panel book and revisions

Interference Check, QA Findings, Materials List, Print, Revision History

In ConstructiVision you set up the site record first: units, project, grid, walls and slab. Then you design every panel. Then you return to the site drawing for the casting layout and the crane plan, because both need the finished panels’ sizes, weights and pick points. The job runs the same way: the panel layout is planned before casting, and it is only final once the panels are.

Warning

Crane stations belong fully outside the wall clearance or fully inside the closure strip, never across the slab edge. A crane with one track on the slab and one on unpoured ground can tip under load. Check every station in the crane plan against this before you issue it.

The panel, in the order it is built on the bed

1. Main dimensions and the form

what

button

Width, thickness, bottom and top elevations, peak or arch

Edit Main Panel

Edge miters, expansion gaps, gridlines and the corner condition

Edit Main Panel

The casting face (which face is down), and the dimension and elevation references

Edit Main Panel

For an insulated sandwich panel: exterior wythe, insulation and wythe connectors

Sandwich Panel

Top steps and footing steps, the outline of the form

Top Step, Footing Step

You set the sandwich layers here because they divide the panel’s thickness. In the field, the exterior wythe, insulation and connectors go down in step 4, before the structural wythe’s reinforcement.

2. Cuts through the full depth

what

button

Windows and other standard openings

Standard Opening

Man doors

Man Door

Dock levelers

Dock Leveler

Rough openings

Rough Opening

3. Partial-depth shaping

what

button

Recesses and blockouts

Recess / Blockout

Pilasters, lintels and thickened edges

Pilaster / Lintel, Lintel Details

Spandrel seats

Spandrel Seat

Chamfer strips on the form edges

Chamfer

4. The down face, laid on the bed before the reinforcement

what

button

Reveals, horizontal and vertical

Reveals, Vertical Reveals

Form liners and other face materials: thin brick, stone, exposed aggregate, sandblast

Exterior Face

Embeds on the down face

Weld Connections, Edit Embeds

5. Edges and reinforcement

what

button

Slab dowels through the bottom edge

Slab Dowels

Reinforcement

not drawn by ConstructiVision

6. The up face and the top edge

what

button

Embeds on the up face

Weld Connections, Edit Embeds

Ledger and top plate

Ledger / Top Plate

Roof line

Roof Line

Weld Connections appears once on the toolbar, with the down face. Use it in step 4 for the down-face rows, and again in step 6 for the up-face rows.

7. Last: lifting and bracing

what

button

Pick points (lifting inserts)

Pick Points

Brace points (bracing inserts)

Brace Points

The data the panel specialty engineer or insert supplier needs

Export lift-engineering data

These come last because their positions depend on the panel’s weight, its centre of gravity, its openings and its embeds, and those are final only after steps 1 to 6. The lifting and embed design itself belongs to the panel specialty engineer.

8. Check and issue

Check the weight, centre of gravity, area and volume in the title block. Run the interference check on the site, print the shop drawing, and add a revision stamp when a released panel changes. See Print a panel book and Track revisions.

The Main Panel feature checklist

The Panel Features toggles in the Edit Main Panel dialog follow the same order, six to a row:

row

toggles

1, cuts and partial depth

Standard Opening, Man Door, Dock Leveler, Recess/Blockout, Pilaster/Lintel, Chamfer

2, face, connections, edges

Reveal, Weld Connections, Slab Dowels, Ledger/Top Plate, Roof Line, Pick Points

3, the last step

Brace Points

Where the order comes from

The order follows these sources. Each one names the step it supports.

  • Regulation. OSHA 29 CFR 1926.704(a): tilt-up wall panels “shall be adequately supported to prevent overturning and to prevent collapse until permanent connections are completed”. This is why the braces come off last. OSHA 1926.704

  • Industry standard. ACI 551.1R-14, Guide to Tilt-Up Concrete Construction: preconstruction planning; the floor slab as the casting bed, with slab closure strips; forming and casting in the order forming, architectural treatments, reinforcement, embed plates, lifting and bracing inserts, then concrete placement; and sandwich panels.

  • Industry standard. TCA, Safety Guideline for Tilt-Up Concrete Construction, version 13.1 (June 2013): the checks before construction, before lift day, during the lift and after it. TCA Safety Guideline (PDF)

  • Industry standard. ACI 551.2R-15, section 11.4: the lifting and embed design belongs to the panel specialty engineer.

  • Best practice. D. Greive and D. Buzzelli, “Speed to Market and Slab-On-Grade Performance in Tilt-Up Construction”, Tilt-Up Today, 2026: the site sequence above. Article

  • Best practice. J. MacKinnon, “Considerations When Designing and Building A Tilt-Up Project”, Tilt-Up Today, 2007: every project needs a panel layout diagram showing where each panel is cast on the slab. Article

  • Best practice. E. Sauter, “Panel Forming”, Tilt-Up Today, 2007: edge forms, then door and window blockouts, then reveals, then bond breaker, then reinforcing and embedments. Article

  • Best practice. D. Dixon, “Insulated Sandwich Panels”, Tilt-Up Today, 2008: the exterior wythe, insulation and connectors first; interior reinforcing, lifting and bracing hardware in the second pour. Article

ConstructiVision does not design reinforcement. Hand that, and the lifting and bracing design, to the engineer of record and the panel specialty engineer.